Nassau, The Bahamas – The Ministry of Public Works and Transport advises the public of the progress of the New Providence Road Improvement Project.

The Ministry advises motorists that Robinson Road is opened to traffic between Blue Hill Road and Fourth Street.

The Market Street junction has been paved. Motorists can connect with Robinson Road if they are travelling south on Market Street.

All of Robinson Road is now paved and open to traffic including the Market Street/Robinson Road junction.

Prince Charles Drive between Pine Barren Road and just east of St. Augustine’s College back entrance will be paved by the end of this week.

The closure of Wulff Road from the roundabout at Marathon to Kemp Road will be opened to vehicular traffic by next week Monday.

Further, the Ministry advises motorists that Baillou Hill Road (south) northbound, between Ameryllius and Independence Drive is closed daily between 9 am to 6 pm. This closure will last for one week to facilitate excavation for the installation of water mains and service ducts.

The western side of the junction at Soldier Road/East Street and the eastern side of the junction at Baillou Hill/Solider Roads are currently closed to allow trenching for underground works. The alternative route is Malcolm Road.